30 December, 2014
During the period of time 2013 – 2014 Advice Turboinzhiniring" Company Limited in cooperation with «Bilfinger Gerber GmbH” conducted the work on modification of two LM 6000 gas turbines Air Intake System (AIS), installed on Power Generation units 1,2 on PGU 110 Astrakhanskaya GRES (LUKOIL-Astrakhanenergo). Main target of the modification – cooling of gas turbine intake air – was realized by means of design, manufacture and installation of new AIS (with chillers and pulse cleaning system integrated) instead of old one. Project was fulfilled under the Contract signed with General Contactor “ICL Engineering” Company (Astrakhan city).