Development of LM6000 Air Intake System (AIS) retrofit project
+7 (812) 493 42 44
Russia, 192019, Saint-Petersburg naberezhnaya Оbvodnogo kanala 14, liter C, office 312
news
In July 2021, our company completed a project on modernization of silencer desig...
Last year our company began cooperation with English company CULLUM Detuners Ltd .
In January 2019 Advice Turbine Engineering (ATE) made a last shipment of the spa...
News archive
Development of LM6000 Air Intake System (AIS) retrofit project
10 August, 2016
In August, 2016 a new set of cooling modules for modernization of third LM6000 gas turbine AIS was supplied at PGU 235 Astrakhanskaya GRES. Previous shipment of equipment for modernization of the second LM 6000 gas turbine was delivered in May 2016. Thus, unlike the set of equipment shipped for retrofit of the first LM 6000 and taking into account Customer’s comments the adjustments for the pre filtration components were made - the design of the anti mosquito nets and G4 filters has been changed.