20 April, 2017
During period of April 14 – 18, 2017 specialists of our company took part in supervision of erection of modified Air Intake Systems on the Astrakhanskaya GRES PGU 235 production site.
The Assembly and fit of standard AIS modules with upgraded cooling modules was produced at the ground (“0”) level at first and after the presentation to the Customer was installed on the original location of the gas turbine.
Work on dismantling of the "old" AIS design, installation of the "new" modified one and run of gas turbine in operation was made during the week.